18 May 2012

Along the Baobab Boulevard

Baobab trees (Adansonia) are fascinating trees. At glance their unusual "bottle-like shape" immediately draws attention of any curious hiker. They are many species of this tree originated from Madagascar: They do bear heat and some have adapted to coastal regions. Digging out a bit more, one learns that they don't produce annual growth rings, which make difficult to determine their age. Carbon 14 methods (radiocarbon dating) are then used and confirm that they can grow for some of them extremely old (>1000 years) reaching impressive heights and sizes. In dry seasons they can even store water inside their swollen trunks. On the top of that, seeds, fruits and leaves have edible qualities among other uses.
Last but not least, have you ever seen a baobab flower? At day it looks passed or withered and surprisingly, this miserable flower takes all its beauty at night: the white colour becomes then a little sun in the night.

Young baobabs have been successfully planted close to the Roches district in Kourou. So don't look for the Sunset Boulevard but just enjoy a jogging early morning when it is still fresh between the beach and the Baobab boulevard....

17 May 2012

No Comment

Fourmis Atta/Atta ants, CSG, Kourou 17/05/12

Preparing for fuelling

...Cryogenic age has not spread over the Kourou river, or a new glaciation era has not suddenly hit French Guyana as it may be suggested by the picture below...
This is just the quiet Kocher river in Sindringen last January. A romantic place in the Baden-Württemberg near Lampoldshausen where the propellant drums for MSG were produced by ASTRIUM and were accepted by ESA and Thales before shipment by road and boat to Degrad de Cannes, the Cayenne harbour.
Two drums are needed to fuel MSG: one for MON, one for MMH plus two back up drums (i.e. four drums in total).
Here under is a representation of one of these highly securised containers.
The scale enables to reach the top of the drum for the leak detection measurements on the flanges, valves and manometers... these measurements are repeated at various steps of the transport to make sure that the drums are tight.
The fuelling (MON and MMH) will be done in EPCU S5B facility which has been already described in a previous message.
But...another operation will take place before the fuelling: The pressurisation of the Helium tank to 260 Bars (this operation will still be done in EPCU 5C). This inert gas will play the essential role in orbit to pressurise the MON and MMH tanks to about 13 bars in order that the different satellites manoeuvres required for the mission can be achieved. 85% of the propellant will be consumed within the first 2 weeks of the mission for the proper firing of the two Liquid Apogee Motors (LAM). With four Apogee Motor Firings (AMF), MSG-3 will move from the (elliptical) transfer orbit to its Geostationary position. The remaining 15% of propellant gas will be used for the usual orbit and attitude control manoeuvres performed by the thrusters during the 7 year nominal life time... and very likely more.
The Helium tank filling will be made using the Fill and Drain Valve (FDV), the last blue cap on the left, located just under the battery as showed on the picture below. The four other FDVs are used for testing only. Note that the Multi Layer Insulation (MLI) is not completely installed for permitting this filling operation.
As the filling is an hazardous operation (static and dynamic risks linked to pressurisation), two large  protective"walls" called blasting shields have been installed in the S5C clean room.
When the Helium pressurisation will be completed by mid of next week, the walls will be removed and MSG-3 will be transported to S5B for the fuelling.
By the way, all walls have eventually to be removed one day... or painted to tell their story!
Berlin, Postdamer Platz, June 6th 2010.
Note: The technical part of this message was proof read by Rolf our propellant expert 

15 May 2012

Successfull VA206 launch

On 15/05/2011 at 19:13 sharp, Ariane 5 successfully lifted off the 2 Asian spacecrafts Vinasat-2 (Vietnam) and JCSAT-13 (Japan). Those two telecommunication satellites were manufactured by Lockheed Martin Commercial Space System.
This is obviously an important date as far as this success clears up the way for the next Ariane 5 launch: VA207 for Ecchostar-17 and... MSG-3.

MSG teams followed live the VA206 launch from various sites: the beach near by Hotel des Roches or Jupiter, Agami and Toucan which are three controlled CSG observation sites.
This was really an impressive launch.
Here after are displayed few pictures shot from the Toucan observation point of view...

Family picture(s) - 1

On 15/5/2012 few family pictures have been made in the clean room as our "baby" is getting more and more elegant. These few pictures also reflect the presence of the various MSG-3 teams at the CSG for the moment. There will be other family picutres in the future as it is impossible to have all the team members available on the spot at the same time...
This was a also a special moment to celebrate the good team spirit since the MSG-3 campaign started and also the good work accomplished so far.
ESA team(from left to right): Stefano, Francois, Louise and Cyril
 Credits: Jean-Claude P.
ESA and EUMETSAT teams (from left to right): Jean-Claude, Stefano, Francois, Gianfranco, Margareth,Louise, Antonio and Cyril
 Credits: Jean-Claude P.
Congratulations to the Thales team: This date is really an achievement for all of them!
 Credits: Jean-Claude P.
All together: Thales, ESA, EUMETSAT, and CSG teams!

14 May 2012

No Comment

Ariane 5 VA 206 (Vinasat/JCSAT 13); Roll out from BAF to ELA-3, 14-05/2012 @ 12:00, CSG, Kourou, French Guiana

13 May 2012

Guyenese Tartans

Even if we are here in French Guiana very far from Gaelic or Highlands Scottish cultures, colors and motives printed on fabrics (may be some are even woven) may remind somehow tartans. They draw attention by their bright colors and combinations rather than by their geometry. Could we say that these colors purposely remind those of the various exotic fruits produced here or the sea and sky shades? Anyway, these fabrics are used in the daily life  as (table) clothes, scarfs... or as decorating marks to identify local products (e.g. jam, syrups...). They are frequently met not only in French Guiana but more generally in the Antilles and known as Madras cloth (or Madras tissu in French).

12 May 2012

Almost dressed to kill

In order to complete the  electrical testing, Solar Arrays (SA) have been (re) mounted for testing on the spacecraft and the protection covers removed. Tests which have been performed are called "flood tests". The spacecraft was powered by its own batteries and the SAs were, one by one "flooded" with light generating as expected electrical current.The successful performance of this test proved that everything was properly connected and Telemetry (TM) was indicating that the solar panels were illuminated. The good health of the SAs was checked last February in Cannes by the successful performance of flasher tests.
The picture below shows MSG-3 as it was configured for the flood test.
Here under, a closer view on the solar cells (Silicone type) at the bottom edge of the SA.
The flood test was successfully completed by a grounding tests.
Then MSG-3 was straighten up...
Credits: Emilio
to be ready as from 14/05/12 to start the antenna connection tests.
As it can be seen below, a horn mast opposite the the MSG-3 antenna platform has been installed on the transportation dolly for that purpose.
There are four types of antennas on MSG:
  • S/L Band TPA, the large part of the black cylinder
  • S Band TTC, the tip on the black cylinder
  • UHF Band EDA (white crosses)
  • L Band EDAs (small tips on the silver cylinder)
A glance at MSG-3 as it stands now in the clean room shows a close configuration to the one that will hopefully fly next month. Obviously few thermal blankets still need to be mounted to cover the rectangular Solar Array cut outs.
For keeping memory of this milestone, few official pictures have been taken by the ArianeSpace photographer.
That is why we dare to say that as from today MSG-3 is already almost dressed to kill...

Introducing EPCU S5B

If the schedule is met, MSG-3 is planned to move by end of May from EPCU S5C (where it is now tested) to S5B where it will be fuelled. The fuelling is for a satellite equivalent to go to a pump station for car. The difference being in the type of fuel to be delivered and the associated hazards linked to fuelling operations.
Hereunder is an external view on the EPCU S5B (fuelling) building at the CSG.
MSG propulsion, like many other spacecrafts and rockets, is achieved by a classical bi-propellant system, i.e. the combustion of two components: a liquid fuel with a liquid oxidizer.
For MSG-3 the fuel is the  Monomethylhydrazine (MMH) and Mixed Oxides of Nitrogen (MON) the oxidizer.
These two substances should NEVER EVER be in direct contact except in the combustion chamber of the rocket or satellite engines.Therefore, as showed by the picture below, the handling of these two substances follows physically separated routes: one on the right for the MON and another one on the left for the MMH.
At the moment, MSG "drums"containing these two propellants are still in a remote fuel farm (also called ZSE for Zone Stockage d'Ergol).
The S5B facility which has now been accepted for MSG-3 fuelling is now under preparation for performing this operation.
Inside S5B clean hall, Thales staff is validating a special device called DMRP  i.e. Dispositif Mobile de Remplissage et de Presurisation (Fill and Drain Cart). Note there is one cart for the MON and one other for the MMH.
The view below gives an idea of the area where the tank filling will be made. After a transfer from the airlock through the door into the clean hall with a crane, MSG-3 will be put in the middle on the fuelling stand. On the opposite side of the clean hall the MON and MMH rooms will accomodate drums. After being weighted, the MON drum will enter the clean hall the first. When the MON filling is completed, MMH filling will take place. In between decontamination operations is carried out in order to remove any residues of these (extremely) toxic substances inside the facility as well as in the filling material.
The fuelling stand on which MSG-3 will be installed for the fuelling
The propellant team will operate with SCAPE suits (a kind of diving suit) in 4 hour session shifts. The limitation is made by the battery of the radios. Before to don-off  their filling gear, operators have to take a shower. Facilities are foreseen just next to the filling hall.
Before and after the fuelling, the spacecraft is powered on, there fore a cooling device in necessary for the battery. The MICE used in S5C (see previous message), becomes an ICE (for Indoor Cooling Equipment) as it is built-in the facility and no longer a mobile device.
Once the fuelling is made, the SC will move to another area: the BAF (Batiment d'Assemblage Final or Final Assembly Building). At this moment the launch campaign turns into a new phase. The mating on the rocket is getting closer... but we shall let that open for further reporting :-)

11 May 2012

Love letters

On 11/05/2012, the acceptance of the EPCU S5B area, where MSG-3 will be fuelled, took place. S5B is an hazardous processing facility (HPF) which will be described in more details in a dedicated message.
Once fuelled, each Spacecraft (SC) is transferred from this S5B building to the BAF (Final Assembly Building/Batiment d'Assemblage Final) where it will be mated on an Ariane 5 rocket. The transport between these two places will be carried out with the CCU (Container de Charge Utile/Payload Transporter Container).
The (empty) CCU-2 is now ready in S5B for further MSG-3 use and can be seen in the transfer hall.
Once the SC is loaded onto the CCU, this is the last moment the propellant teams may see their own "baby". Therefore, this emotional moment often triggers some farewell words, ranging from love letters to humoristic slogans as it can be seen below...
"it was not always easy and sometimes you made my life miserable. Whatsoever there was great moments!, For all of us and for my daughter (7 months old), that I missed a lot, after 4 weeks drinking Rhum, show us how brave you are..."
David, Mechanical chief
CCU-2 tagging may also offer new perspectives for anonymous artists...
Finally, the presence of old project stickers reveals that this CCU-2 was already used in the MSG-2 launch campaign (2005). Unfortunately the signatures of the propulsion team and the launch manager were erased by effects of time or erosion...
Anyway, Archaeology is never far when working on MSG project :-)